A commercial Solar PV system should be sized around how much electricity the site uses, when it uses it and how much of the solar generation it can make productive use of. Roof space obviously matters, but simply filling every available area with panels does not automatically produce the best commercial result.
For a funded Power Purchase Agreement project, good Solar PV system sizing needs to consider electricity consumption, half-hourly demand, expected solar generation, self-consumption, roof performance, export capacity, future electricity demand and the economics of the PPA itself.
A real commercial project reviewed by ELS shows why. We looked at three Solar PV system sizes for the same business. The smallest achieved the highest self-consumption, while the middle option produced the highest modelled first-year saving. The largest system, meanwhile, supplied the greatest percentage of the site’s overall electricity demand.
So there was no simple “biggest is best” answer.
What determines the right commercial Solar PV system size?
The right size is normally the system that creates the strongest balance between generation and usable electricity demand.
Before deciding how much Solar PV to install, a business needs to understand how much electricity the site uses, when it uses it and how much solar power could be generated during those periods. We also need to consider how much surplus electricity may need to be exported and whether the business expects its electricity demand to change in the future.
Those questions tell us far more than roof area alone.
Why isn’t annual electricity consumption enough?
Annual consumption gives us a useful starting point, but it only tells us how much electricity a business uses over the course of a year. It does not tell us when that electricity is being used, and that can make a significant difference to Solar PV system sizing.
Imagine two businesses each consuming 1.3 million kWh per year. One operates predominantly during daylight hours, while the other uses a large proportion of its electricity overnight. Their annual consumption may be identical, but their ideal solar systems could look very different.
That is why the real commercial project reviewed by ELS used half-hourly electricity consumption data when the three system options were modelled. This allowed expected solar generation to be compared with actual site demand throughout the day, providing a much more useful basis for sizing the system than annual consumption alone.
What is solar self-consumption?
Solar self-consumption is the percentage of electricity generated by the Solar PV system that the business uses onsite. If a system generates 100 units of electricity and the business uses 80 of those units itself, its self-consumption is 80%.
In the ELS project, increasing the size of the solar installation increased total generation but reduced the percentage of electricity that could be used immediately onsite:
| Solar PV system | Modelled self-consumption |
|---|---|
| 427.5kWp | 90% |
| 652.5kWp | 75% |
| 877.5kWp | 63% |
This does not mean that the smallest system was automatically the best option. It simply means that a greater proportion of everything it generated could be consumed directly by the business.
Battery storage can sometimes increase self-consumption further, but that does not automatically improve the financial result. Our analysis of commercial battery storage in the UK shows what happened when an 880kWh battery was modelled on this same project.
The commercial decision needs more context than self-consumption alone.
What is the difference between self-consumption and self-sufficiency?
These two terms sound similar, but they measure different things.
Self-consumption tells us how much of the solar electricity generated is used onsite. Self-sufficiency, on the other hand, tells us how much of the site’s total electricity requirement is being supplied by solar.
The difference becomes clear when we look at the three modelled systems:
| Solar PV system | Self-consumption | Site electricity demand supplied |
|---|---|---|
| 427.5kWp | 90% | 27% |
| 652.5kWp | 75% | 33% |
| 877.5kWp | 63% | 37% |
As the system became larger, self-consumption fell because the business could not immediately use as much of the additional generation. At the same time, however, solar was supplying a greater percentage of the site’s total electricity requirement.
That is why neither number should be considered in isolation.
What happened when three commercial Solar PV sizes were compared?
The clearest way to understand the sizing decision is to look at the three options side by side.
| 427.5kWp | 652.5kWp | 877.5kWp | |
|---|---|---|---|
| Year-one generation | 398,409kWh | 587,315kWh | 771,823kWh |
| Self-consumption | 90% | 75% | 63% |
| Site demand supplied | 27% | 33% | 37% |
| Proposed PPA rate | 10.9p/kWh | 11.9p/kWh | 12.95p/kWh |
| Modelled first-year saving | £31,342 | £34,178 | £32,828 |
The largest system generated considerably more electricity, but it was the 652.5kWp option that produced the highest modelled first-year saving.
The smaller 427.5kWp system achieved the highest self-consumption, while the 877.5kWp option supplied the greatest proportion of the site’s total electricity demand. Each system therefore created a different commercial balance.
You can see the complete financial comparison in our real Solar Power Purchase Agreement example.
This is exactly why commercial Solar PV sizing should begin with the energy data and the objectives of the business rather than simply asking how many panels can be fitted on the roof.
How does roof orientation affect system sizing?
Not every area of a commercial roof will necessarily offer the same generation potential.
In the project reviewed by ELS, the smaller system concentrated on the more favourable roof areas first. As the proposed system became larger, additional roof space was brought into the design.
That means adding more panels may continue to increase total generation, but the additional panels may not necessarily perform on exactly the same basis as those positioned in the strongest locations. Roof orientation, shading and the physical layout of the site can all affect expected yield.
So the useful question is not simply, “How many panels can we fit?” It is also, “What is each part of that proposed system expected to contribute?”
Why does future electricity demand matter?
Commercial Solar PV systems can remain in operation for decades, so sizing a project purely around today’s consumption can sometimes be short-sighted.
A business may expect its electricity demand to increase because of EV charging, fleet electrification, electric heating, refrigeration, new machinery, increased production, longer operating hours or site expansion. If those changes are likely, they should be factored into the initial system design.
The real proposal reviewed by ELS specifically considered this. If electricity demand increased in future, the larger Solar PV option could become more attractive because the business would be able to use a greater proportion of the additional generation onsite. If demand remained fairly static, however, a smaller system with higher self-consumption might provide a stronger fit.
The right Solar PV system should therefore reflect where the business is going as well as where it is today.
Can grid export limits affect Solar PV system size?
Yes. A business cannot automatically assume that all surplus electricity can simply be exported to the grid.
The project reviewed by ELS was subject to a DNO G99 application to establish how much export capacity was available. This becomes increasingly relevant as Solar PV systems get larger because the amount of electricity not consumed onsite may also increase.
Commercial system sizing therefore needs to consider both sides of the equation: how much electricity the site can use itself and what will happen to any generation it cannot consume.
How does a PPA change the sizing decision?
A Power Purchase Agreement adds a financial layer to the energy modelling.
Under a PPA, the project needs to work commercially for both the customer and the funder. Expected generation, onsite consumption, PPA pricing, minimum consumption commitments, export, agreement length, system cost and future demand all feed into that calculation.
This means the objective is not simply to maximise installed capacity. The goal is to design a project where the Solar PV system, the electricity usage and the funding structure make sense together.
The three options in the real project demonstrate this well because each system size also came with a different PPA rate and a different financial outcome.
What information is needed to size a commercial Solar PV system?
A useful first assessment normally needs more than the dimensions of the roof.
Ideally, we would want:
- at least 12 months of electricity consumption data
- half-hourly consumption data where available
- site operating hours
- roof or site information
- current electricity costs
- planned EV charging or electrification
- expected business growth
- any known export constraints
- the preferred funding structure
This gives us a much clearer picture of how the business actually uses electricity and what it may need in the future.
The more accurately that demand profile is understood, the more useful the Solar PV modelling becomes.
So how big should a commercial Solar PV system be?
There is no standard answer.
The right commercial Solar PV system is the one that best matches the site’s current and future electricity demand while producing a sensible commercial result.
The project reviewed by ELS demonstrates that clearly. The smallest option achieved the highest self-consumption, the middle system produced the highest modelled first-year saving, and the largest option supplied the greatest percentage of the site’s electricity demand.
Each answered a slightly different commercial objective, which is why the right decision depends on what the business actually wants the project to achieve.
Considering commercial Solar PV under a PPA?
If your business is considering a commercial Solar PV installation, the starting point should be your electricity data rather than the number of panels that can fit on the roof.
ELS can work with the customer, supplier and funding partner to look at system sizing, expected generation, onsite consumption, future demand, the proposed PPA funding structure and the overall commercial outcome.
We start by understanding how your business uses electricity, then work backwards to the system that makes sense.
The figures used in this article are based on an anonymised commercial Solar PPA proposal reviewed by ELS. Generation, consumption and savings figures are modelled rather than guaranteed. Final projects remain subject to technical assessment, structural suitability, DNO requirements, energy performance and final commercial terms.